Construction and Commissioning of Transformer Substations TS2 and TS3 – Belgrade Waterfront
As part of the project at the prestigious Belgrade Waterfront – Plot 24 location, we successfully completed the construction and commissioning of two transformer substations: TS2 and TS3, each with a capacity of 2×630 kVA, voltage ratio 10/0.42 kV.
Project Overview:
Both substations are located on the underground level of a shared parking structure of two residential buildings, directly across from the Galerija Shopping Center.
Scope of work included:
All equipment used in the project was provided by the renowned manufacturer Schneider Electric, for whom we, Elektrovat, are official partners.
Location and Importance:
This project forms a key part of the dynamic development within the prestigious Belgrade Waterfront residential and commercial complex. Execution required a high standard of quality and precise coordination of all on-site activities.