Small hydroelectric power plant Beli kamen

General contractor: Elektrovat LTD, Belgrade

Investor: Zlatibor Power Plants

During the implementation of the small hydroelectric power plant, the following was done:

  • Construction of access roads;

  • Construction of a hydraulic tunnel, 450 m long;

  • Production of pipelines 2700 m in length, water intake, sedimentation tanks;

  • Construction of machine hall, and installation of complete electrical installations;

  • Delivery and installation: MV switchgear 35kV, water turbine (1150kW + 470kW) and generator (1500kVA + 700kVA);

  • Delivery of cable  and installation of cable routes;

  • Connection of power cable in Substation Zlatibor 3, 35 / 10kV;

  • Excavation of the trench and laying of the connecting cable, total length 11700 m;

For privacy reasons YouTube needs your permission to be loaded. For more details, please see our Privacy Policy.
I Accept

For privacy reasons YouTube needs your permission to be loaded. For more details, please see our Privacy Policy.
I Accept

QUALITY GUARANTEE

High quality and business level of our company have been awarded an official acknowledgment via receiving certification for establishing Quality Management System (QMS) ISO 9001:2015, Environmental Protection Control System ISO 14001:2015, Occupational Health and Safety Management System OHSAS ISO 45001:2018 and Certificate of which we are particularly proud of – Energy Management System ISO 50001:2018 and Information Security Management Certificate ISO/ IEC 27001:2014

HOW CAN WE HELP?

Do you need assistance with some project of yours, or you simply want to explore your options… don’t hesitate!

WORKING HOURS

8:00am – 4:00pm

WORKING HOURS

8:00am – 4:00pm