Enhancing production capabilities for Minth Serbia Factory in Loznica

Elektrovat is proud to have collaborated with Minth Serbia Factory in Loznica on crucial electrical works aimed at enhancing production capacities. Our company has been engaged in the execution of electrical power installations and equipment delivery for substations, providing comprehensive solutions ensuring the safety and reliability of the electrical infrastructure. In collaboration with Konstruktor konsalting d.o.o. from Belgrade, Elektrovat successfully carried out multiple phases of this project, including the production and installation of LV switchgear.

LV Switchgear Production and Installation for industrial facilities like Minth Serbia Factory in Loznica.

Project Details:

  • Execution of transformer station installation 35/0.4 kV/kV, 2×1250 kVA.

  • Execution of electrical power installations and delivery of equipment for the substation 35kV/0.4kV, 2x2000kVA in production hall PL07, workshop production of LV switchgear 4000A.

  • Electrical works on the production of electrical energy installations and delivery of equipment for the substation 35kV/0.4kV, 2x2500kVA in production hall PL04, workshop production of LV switchgear 4000A.

  • Electrical works on the production of electrical energy installations and delivery of equipment for the substation 35kV/0.4kV, 2x2000kVA in production hall PL05, workshop production of LV switchgear 3200A.

  • Workshop production, installation, and connection of LV main distribution cabinets in halls PL04 and PL05 (20 pcs) and installation of supply lines.