Continental Automotive Serbia – Kać, Novi Sad

Continental Automotive Serbia, a global leader in sustainable mobility technologies, is expanding its presence in Serbia through innovative projects. With headquarters in Subotica and Novi Sad, where their key factories and research and development center are located, Continental is dedicated to advancing technological solutions for vehicles and transportation.

Electrovat is proud to be a part of this process through our recent project with Continental. Here, we will reveal the details of our work, the role we played, and how our partnership contributes to the advancement of the industry.

Continental Automotive Serbia - Kać, Novi Sad

The project was successfully completed with the utmost attention to technical standards and client requirements. All systems were delivered, installed, and commissioned in accordance with the highest industry standards, ensuring reliable and efficient operation of Continental Automotive Serbia’s facilities in Kać, Novi Sad. For Continental Automotive Serbia, Electrovat performed the following tasks.

  • Delivery and Installation of Equipment with Commissioning in the Switchgear Facility PRP:

    • Installation of 20kV switchgears type SM6 in two sections.
    • Installation of 3 distribution cabinets.
    • Configuration and parameterization of microprocessor protection relays.
  • Execution of Site Electric Power Installations.

  • Building EP1.1 Production, Clean Room (PRO, CR) and Building EP1.2 Technical Building (TEH):

    • Installation of 20kV cable lines for the Production and Technical buildings.
    • Execution of outdoor lighting installations.
    • Execution of transformer station installations:
      • Transformer station TS Production: 20/0.4kV, 2x2500kVA.
      • Transformer station TS Technical Building: 20/0.4kV, 3x2500kVA.
    • Execution of busbar trunking system installations (630A) in the Production building (750m).
  • Project E-002:

    • Building Production, Clean Room (EP1.1): Execution of electrical power installations and lighting installations, diesel electric generator installation (900kW), installation of smoke extraction system, and installation of solar blinds.
    • Technical Building (EP1.2): Execution of electrical power installations and lighting installations.
  • Design and Installation of a Photovoltaic Power Plant

    • Development of Project Documentation: Comprehensive preparation of project documentation for the construction of a photovoltaic power plant with a total capacity of 900 kWp.
    • Electrical Installation Works: Execution of electrical installation works, including the installation and connection of photovoltaic panels, inverters, and associated equipment for efficient solar energy production.
    • Commissioning: Testing, configuration, and commissioning of the photovoltaic power plant. System parameterization for optimal performance and integration into the existing electrical grid.