Photovoltaic power plant for Oil refinery in Novi Sad

We proudly present our latest endeavor in partnership with Naftna Industrija Srbije a.d. – Novi Sad. Our focus lay in the meticulous construction of a solar power plant with a total power of 6,59 MWp coupled with the implementation of a sophisticated SCADA system, ensuring efficiency and sustainability.

we proudly present our latest endeavor in partnership with Naftna Industrija Srbije a.d. - Novi Sad. Our focus lay in the meticulous construction of a solar power plant coupled with the implementation of a sophisticated SCADA system, ensuring efficiency and sustainability.

Project Overview:

  • Development of project documentation and execution of construction and electrical installation works for a solar power plant.

  • Fabrication and delivery of four metal-clad substations (LTS3 20/0.8kV, 2000kVA, LTS4 20/0.8kV, 2000kVA, LTS7 20/0.8kV, 1600kVA, LTS2 20/0.8kV, 1600kVA).

  • Design and deployment of a SCADA system for visualization and management of the solar power plant.

  • Successful commencement of operations for the solar power plant.

QUALITY GUARANTEE

High quality and business level of our company have been awarded an official acknowledgment via receiving certification for establishing Quality Management System (QMS) ISO 9001:2015, Environmental Protection Control System ISO 14001:2015, Occupational Health and Safety Management System OHSAS ISO 45001:2018 and Certificate of which we are particularly proud of – Energy Management System ISO 50001:2018 and Information Security Management Certificate ISO/ IEC 27001:2014